Standing Rigging Replacement Log -- Done winter of 2019-2020 See Standing Rigging
- Disconnect anenometer cable and thread through cockpit lockers, cabin, head, v-berth, and out of the boat. Coil and tie to mast. -- Done 2020-02-28
- Disconnect VHF cable and thread through cabin, head, v-berth, and out of the boat. Coil at bottom of mast. Coil and tie to mast. -- Done 2020-02-28
- Disconnect anchor and steaming lights electrical wiring. -- Done 2020-02-28
- Use electrical tape to mark marine studs on shrouds and backstay. -- Done 2020-02-28
- Untie halyard leader from boom, pulpit, etc. Coil and tie to mast. -- Done 2020-03-02
- Remove boom. -- Done 2020-03-02
- Label shrouds and backstay. -- Done 2020-03-02
-
- Move boat to the site of A-frame. -- Done 2020-03-04
- Loosen shrouds and backstay. -- Done 2020-03-04
- Unbolt mast base from deck. -- Done 2020-03-04
- Disconnect shrouds and backstay. Loop upward and secure to mast. -- Done 2020-03-04
- Disconnect headstay. Walk it aft, outside spreaders and A-frame, as the mast is lowered. -- Done 2020-03-04
- Lift mast very slightly. -- Done 2020-03-04
- Lower mast to rest on bow and stern pulpits as well as cushion on deck. -- Done 2020-03-04
- Remove shrouds and backstay, replacing clevis pins in marine eyes as we go. -- Done 2020-03-04
- Lift mast off boat and place on supports on land. -- Done 2020-03-04
- Return boat to slip. -- Done 2020-03-04
-
- Measure length and diameter of shrouds and backstay. -- Done 2020-03-08
-
- Remove mast base and have replacement fabricated. -- Done 2020-04-06 provided broken mast base to Eastport Spar & Rigging
as model for replacement $600.
- Evaluate condition of lower shroud triangles and through-mast connecting pin. -- Acceptable
- Order replacement shrouds and backstay with swage marine eyes at top end. Order new clevis pins and cotter pins. -- Done
- Examine condition of gooseneck. Consider replacing gooseneck bolts with clevis pins. -- Acceptable
-
- Install replacement Windex 15
. -- Done 2020-05-07
- Install and connect using AWG16 LED Windex Light
illumination bulb. -- Done 2020-05-07
- Install and connect using RG-8X
, the Metz Communications Manta 6 VHF antenna
-- Done 2020-05-07
-
- Remove chainplates.
- Enlarge chainplate bolt holes.
- Fill holes with thickened epoxy.
- Drill new holes for chainplates into the epoxy.
- Reinstall chainplates.
-
- Replace spacer under the gooseneck and spinnaker pole tracks with Derlin. -- Not needed done by a previous owner.
-
- Switch starboard and port spreaders. -- Done
- Examine speader sockets. -- Acceptable
- Examine connection for genoa halyard. (possible metal on metal wear) -- Done some wear, not significant.
-
- Remove headstay from foil. -- Done 2020-03-11
- Measure length and diameter of headstay (1/4"? 6mm?). Current headstay has two extra toggles and one pair of six inch extender plates. 60mm of adjustment via integral rigging screw.
- Order replacement headstay with swage marine eye at top end. Order new clevis pins and cotter pins. -- Done
- Remove topmost foil section and replace with full length (2.4m) section. -- Done 2020-05-15
- Calculate length for lowest foil section. -- Done 2020-05-15
- Cut former top foil section to replace lowest foil section. -- Done 2020-05-15
-
- Reassemble headstay. -- Done 2020-05-15
- Cut new upper shrouds to length and assemble lower Sta-Loks. -- Done 2020-04-26
- Cut new lower shrouds to length and assemble lower Sta-Loks. -- Done 2020-04-26
-
- New Sea-Dog
400010-1 LED fixed mount all around light
. -- Ordered 2020-03-09 from Go2Marine
order #22299, $35. Delivered 2020-03-12. Installed using 16AWG on 2020-05-07 -- Done
- Replace existing Forespar ML-2 LED Combination Deck / Steaming Light
. ~$125. Steaming LED light 0.08A vs 0.8A incandescent. LED Deck light 0.36A vs 1.6A incandescent. Ancor primary cable: 12AWG 31lbs/1000' (triplex: 125lbs), 16AWG 16lbs/1000' (51lbs), 18AWG 12lbs/1000' (49lbs). Primary wire 12AWG 31lbs/1000' 6,500CM, 14AWG 23lbs/1000' 4,100CM, 16AWG 16lbs/1000' 2,600CM. Done 2020-05-07
- Voltage Drop E = 10.75 * Amperes * Feet / Circular Mil Area
-
- Remove and replace main halyard sheave from mast. -- Done 2020-05-14. Arrived 2020-03-27, ordered on 2020-03-22 from Zephyrwerks
- Remove and replace main halyard axle bolt and compression tube. -- Done 2020-05-14. Arrived 2020-03-27, ordered on 2020-03-22 from Zephyrwerks
-
- Move boat to the site of A-frame. -- Done 2020-05-17
- Attach new mast base to mast. -- Done 2020-05-17
- Reeve main, genoa, and spinnaker halyards. -- Done 2020-05-17
- Attach new lower shrouds to mast. -- Done 2020-05-17
- Attach new upper shrouds to mast. -- Done 2020-05-17
- Attach new headstay to mast with three hole stay extender. -- Done 2020-05-17
- Attach new backstay to mast. -- Done 2020-05-17
- Cut backstay to length, install upper Sta-Lok. -- Done 2020-05-17
- Stand mast on boat. -- Done 2020-05-17
- Attach new upper shrouds to chainplates. -- Done 2020-05-17
- Attach new lower shrouds to chainplates. -- Done 2020-05-17
- Attach new headstay to stem. -- Done 2020-05-17
- Attach new backstay to chainplate with a three hole stay extender. -- Done 2020-05-17
-
- Tension rig.